WEIGHTS OF STRUCTURAL STEELWORK FOR VARIOUS FORMS OF STRUCTURE |
||||
|
Unless noted otherwise the figures given are in units of kg / m3. |
||||
|
Where two figures are given, e.g. 6.0 / 0.5, the first represents the quantity of HRS and the second CFS |
||||
|
TYPE OF STRUCTURE |
GRADE OF CONSTRUCTION |
COMMENTS
|
||
|
LIGHT |
MEDIUM |
HEAVY |
||
|
Sheds without cranes:- Single Span - Multi-Span - |
5.0 / 0.8 4.5 / 0.6 |
6.0 / 1.0 5.5 / 0.8 |
7.0 / 1.3 6.6 / 1.2 |
LIGHT - single skin cladding with no services MEDIUM - insulated cladding + services HEAVY - tiled roof and or heavy services |
|
Sheds with cranes:- Single Span - Multi-Span - |
8.2 / 1.0 7.2 / 0.8 |
9.5 / 1.0 8.2 / 0.8 |
12.0 / 1.0 11.0 / 0.8 |
LIGHT - cranes up to 5t + nominal services MEDIUM - cranes up to 20t + nominal services Heavy - cranes over 20t + nominal services |
|
Aircraft Hangars:- Without Cranes - With Cranes - |
6.0 / 0.5 |
6.0 / 0.5 7.0 / 0.5 |
|
Lattice roof girders with lattice or autofab columns assumed. Cranes schemes assume the presence of a load sharing system for local crane loads. |
|
Power Stations:- Turbine Hall - Boiler House - Control Building (elec.+ mech) - Pump House - Canteen / Toilet Blocks - |
16.0 / 1.0
|
20 + Flrs 26 + Flrs 18 12 10 |
26 + Flrs
26 16
|
Traditional coal fired stations assumed. Mini-Combined-Cycle stations will be less than the figures given here.
|
|
Steel Plants etc:- Buildings with Plant and Cranes -
|
12.0 / 1.0
|
20
|
25
|
LIGHT - mills MEDIUM - heavy mills or normal steel plants. HEAVY - heavy iron and steel making plants |
|
Offices:- Low Rise - High Rise - |
8
|
10
|
12
|
LIGHT - small grids and or light construction MEDIUM - grids up to 8m. HEAVY - grids >8m and or heavy floors and roof |
|
Sports Stadia:- Stadium (no accommodation) -
|
4.5 / 0.4
|
6.0 / 0.5
|
10
|
Lattice roof girders at 20m height assumed. The weight of accommodation should be allowed for by using other relevant data given in this table |
|
Football Stands:- With Front Columns - Clear Span to Front - Seating Support Steel only - |
3.0 / 0.6 5.5 / 0.6 45 kg/m2 |
3.5 / 0.6 8.5 / 0.6 60 kg/m2 |
90 kg/m2 |
Lattice roof girders at 20m ht. Floors are extra LIGHT - grids of less than 6m x 12m MEDIUM - grids 6m x 12m (6m x 6m for seats) HEAVY - grids above 6m x 12m |
|
Multi-Storey Car Parks:-
|
10
|
12
|
16
|
LIGHT - small grids about 7.8m x 9.5m MEDIUM - grids about 7.8x12 or 10.4x11.3 HEAVY - grids about 7.8m x 16.5m |
|
Footbridges:- With light weight concrete floor - With steel plate floor - |
55 70 |
65 80 |
100 115 |
LIGHT < 20m span MEDIUM about 20m span HEAVY > 20m span |
|
CADOSS (R) |
Project |
Job Ref |
|||
|
Part of Structure |
Calc Sheet No. / Rev |
||||
|
Drawing Ref |
Calc By |
Date |
Check By |
Date |
|
|
Example 1 - Single Storey Multi-Span Retail Unit |
|
The main steel framed building measures 75m wide x 150m long x 10m mean roof height. Inside the main frame is a two-storey steel framed office and facilities block measuring 6m wide x 25m long which has two storey's of 3m height. Our client requires a budget estimate for the structural steel frame:- Our choice of framing for this project would be a three bay, UB section, portal frame with spans of 25m and a roof pitch of 10deg. Main frames would be spaced at 6m centres. The small office section would be framed with UB beams and UC columns on a 5m x 6m grid, secondary beams at either 2.5m or 3m centres may be used depending on the type of floor units used. Cold formed sections will be used for roof purlins and cladding rails. From the building weights table the type of structure will be Medium duty Multi-Span Shed for the main frame and Light Office for the internal facilities block. |
|
Volume of main building |
= 75m x 150m x10m |
= 112500m3 |
|
Volume of office and facilities block |
= 6m x 25m x 2No. x 3m |
= 900m3 |
|
Weight of, hot rolled, steel in main frame |
= 112500m3 x 5.5kg/m3 |
= 618750kg |
|
Weight of, hot rolled, steel in office block |
= 900m3 x 8kg/m3 |
= 7200kg |
|
Weight of, cold formed, steel in main frame |
= 112500m3 x 0.8kg/m3 |
= 90000kg |
|
Total weight of structural steelwork |
= 715950kg |
= 716 Tonnes |
|
|
|
|
|
For this type of structure in the UK a keen fabricator would probably quote a little under £1000 / t to supply, deliver and erect the building frame. So for our budget price we will assume £1000 / tonne. |
||
|
|
|
|
|
Total cost of structural steelwork |
= 716t x £1000 /t |
= £716,000.00 |
|
_____________________________________________________________________________ |
||
|
Notes 1. The table of building weights includes within it an allowance for fittings together with an equivalent weight allowance for bolts and welds, so these items do not need to be allowed for separately. 2. Rates per tonne for structural steelwork vary widely from one fabricator to another. Rates also vary up and down depending on the economic situation at the time. Once you have your estimated tonnages it would be well worth ring around a couple of fabricators to find out their latest rates. Don't forget to give your fabricator the tonnage breakdown and tell him that fitting, bolts and welds are allowed for in your tonnages. |
|
Document (No. 20011229/WS/002) |
. MG Double © 2002 |
||||