
Case Study - Exmoor
National Park AuthorityAirwave applied for and gained
planning permission for a 20m TETRA mast in a quarry. When they came
to build the mast they decided that it actually needed to be 10m
taller. They built the taller mast without planning permission. Exmoor
NPA tried to get Airwave to discuss alternatives but they declined.
ENPA issued an Enforcement Notice against which Airwave appealed -
requesting a Public Inquiry.
ENPA engaged our services and we quickly identified an alternative
means of providing the service. Despite lengthy correspondence prior
to the Inquiry, Airwave refused to meet to discuss this option.
In a 5 day Inquiry during which Airwave submitted 19 additional
documents, they sought to argue that the alternative put forward was
not practical. The Inspector was not convinced by Airwave's arguments
and dismissed Airwave's appeal. Both sides submitted cost claims. No
costs were awarded.
Mr D. Wyborn, Chief Planning Officer at ENPA wrote to ECS:
"I believe that the Inspector in dismissing the appeal and
upholding the Notice gives a clear vindication of the approach of the
National Park Authority, in not only its judgement but also the
willingness to find alternative solutions. It was your technical input
which made this possible and your advice on the quarry rim mast was
the decisive factor." December 2006.
Downloads:
Appeal Decision.
Cost Claim (ENPA).
Cost Claim
(Airwave).
Case Study - Taunton Deane Borough Council
O2 erected a slim-line monopole under a deemed consent. They did
not build it according to their submitted plans. At the subsequent
enforcement inquiry they argued that the plans were not required as
part of a valid application. They further argued that since they were
marked "do not scale" even through they were scale drawings, that the
Authority was not entitled to place reliance on the drawings. The
Inspector did not agree and the appeal was dismissed.
Downloads: Appeal
Decision. Cost Claim.
Case Study - Hinckley and
Bosworth Borough Council
Faced with an application for a 25 metre high Orange mast in open
countryside, H&BBC decided to refuse the application (twice!). This
resulted in an appeal and a Public Inquiry. Richard Newstead
suggested how the Council should approach the appeal and worked
closely with the Council's barrister. At the Inquiry Orange withdrew
the appeal after the first morning of the hearing - having heard
only our opening statement and our technical evidence-in-chief.
Orange agreed to pay H&BBC a substantial sum towards their costs in
lieu of a formal costs claim.
Case Study - Sefton Borough Council
Orange erected a mast in Southport which the council considered
had been unlawfully erected. They served an enforcement notice.
Richard Newstead was asked to act as the Council's technical
witness. Working closely with the Council and their barrister, he
was able to build a persuasive technical argument in favour of the
Council. The Council was successful in having the appeal dismissed
and won a substantial award of costs against Orange.
Case Study - Test Valley Borough Council
Airwave refused to remove a temporary mast after their permission
had expired. The Council argued that the mast was inappropriate for
a permanent installation. ECS assisted the Inspector in examining
options. The appeal was dismissed.
Read the appeal decision here.
Case Study - Maidstone Borough Council
Faced with a planning application for a mast to cover part of the
Channel Tunnel Rail Link, Maidstone Council had a problem. In
essence, the applicant argued that their site was the only option.
We evaluated this statement and at a Hearing gave evidence to the
contrary. The appeal was dismissed.
Read the appeal
decision here.
Do we always win?
No; inevitably we don't always win. Not all Inquiries revolve
around technical issues but where technical issues are involved, we
have an excellent track record. Contact us for details.