Systems Engineering Management Plan
Section 3.8 - Model Text
The Technical Performance Management (or Measurement)
effort shall be tailored to meet the program (project) needs and
shall be planned and executed.
- 3.8.1 Parameters.
- The Technical Performance Parameters selected
for tracking shall be key indicators of program success. Each
parameter identified shall be correlated within a specific CWBS/SOW
element.
Parameters:
- software performance;
- software tool(s) performance;
- human performance;
- system test performance;
- reliability performance;
- environmental performance;
- quality evaluation performance;
- project management performance.
- Additional parameters shall be added as the necessity
arises.
- The following data, shall be established during
the planning stage for each parameter to be tracked: - specification
requirement; - time-phased planned value profile with tolerance
band; - program events significantly related to the achievement
of the planned value profile (reviews, audits, etc.); - conditions
of measurement (type of test, simulation, analysis, etc.). Metrics
shall be developed to report on the parameters status during the
project system life cycle. Metrics data shall be gained from audit
reports (internal and external), review reports (internal and
in-process), test reports, minutes of meetings, quality evaluation
records, configuration status accounts, etc. When contractually
specified the specific method and technique will be established
and documented in a detailed procedures document and implemented.
- 3.8.3 Implementation of a TPM.
- As the design progresses, the "achievement
to date" shall be tracked continually for each of the selected
technical performance parameters. In case the "achievement
to date" value falls outside the tolerance band, a new profile
or "current estimate" shall be developed immediately.
The "current estimate" shall be determined from the
"achievement to date" and the remaining schedule and
budget.
- 3.8.4 Relating TPM to cost and schedule
performance measurement.
- TPM shall be related to cost and schedule performance
measurement. Cost, schedule and TPM shall be made against common
elements of the CWBS/SOW.
- 3.8.3 Status reporting of TPM.
- Parameters selected for tracking shall be identified
and their status reported at regular intervals by the 'Technical
Performance Management' status report. The format and content
of these reports shall be in accordance with the status accounting
reports used by configuration management. They shall identify
the parameters selected and identify their status together with
a summary and any recommendations.
LE FastCounter
Back to Home page MANAGING STANDARDS Home page
Please send any beneficial comments or identification of errors
using the following form to: kenr@wysywig.airtime.co.uk
Copyright © by Ken Rigby 1995, 1996, 1997, 1998