Specialists in the design, manufacture and erection of Agricultural, Commercial & Industrial Steel Framed Buildings
Industrial Sector Buildings
PAGE UNDER CONSTRUCTION
Unit and Offices for Bohle UK, Telford - 105 TonnesAn unusual building designed to replicate Bohle head office in Switzerland. This was a design and build project, the building was erected and handed over in two phases, this allowed following trades to start their works asap.
New Industrial Unit at Arrow Valley, Redditch - 510 T130,000sq ft industrial unit with a two story external office block. A design and build project, with a short programme. Completed start to finish in 13 weeks.(9 weeks design and manufacture, 4 weeks on site).